The challenge

  • Severe problems with wastewater pump clogging
  • Pumps broke down and sewage backed up
  • The company needed to macerate the septage flow to protect the pumps and comply with local discharge requirements

The project

  • An in-line 40K Muffin Monster was installed above ground

We’re not having the pump clogging issue at all anymore. The drivers like it too – they don’t have to wait, and they don’t have to muck around with the pumps.

Branch Manager Auckland, Port-a-Loo

The solution

We delivered a 40K Muffin Monster

  • The grinder is able to shred debris that chopper pumps alone cannot handle
  • Drivers can now connect their discharge hose, turn on the shred grinder and unload in 8-10 minutes
  • They also use that time to wash the inside of their tankers

Customer benefits

  • The Muffin Monster grinder saves the company both time and money
  • When 50,000 rugby fans gathered for Britain’s Lions Rugby tour, Port-a-Loo handled collection from more than 500 portable toilets and the Monster worked perfectly
Product
Contact us